Question 1
Q1A financial institution is using VMware Cloud on AWS for a disaster recovery site. During a recent DR test, the failover of a critical database VM using VMware Site Recovery took significantly longer than the target RTO. Analysis revealed that the VM's storage policy was set to FTT=1 (RAID-1), but the DR site's vSAN datastore was nearing capacity. What is the most likely cause for the extended failover time?
Show answer & explanation
Correct answer: C
When a vSAN datastore has low free space, it struggles to find optimal placements for new or moved components. During a Site Recovery failover, powering on the recovered VM requires creating its components on the destination vSAN datastore. With limited free space, vSAN may need to perform many data moves and resynchronizations to satisfy the storage policy (RAID-1), which significantly delays the VM's availability and extends the RTO.