CQE Sample Questions

  1. Question 1

    Intermediate

    What are the major disadvantages of having an improvement team that is too large?I. Difficulty in having constructive input from the entire group.II. Difficulty in arriving at consensus.III. Difficulty in finding large meeting facilities.IV. Difficulty, on the part of the recorder, in keeping up with more paperwork.

    Answer and explanation

    Correct answer: B

  2. Question 2

    Intermediate

    Which of the following is NOT considered a prevention cost?

    Answer and explanation

    Correct answer: D

  3. Question 3

    Intermediate

    An improvement in quality costs is MOST clearly indicated when:

    Answer and explanation

    Correct answer: D

  4. Question 4

    Intermediate

    During the building phase of improvement team development, which of the following properly describes team activities?I. The team leader is usually directive.II. The team leader often delegates tasks.III. Team members prioritize and perform duties.IV. Team members are uncertain of their duties.

    Answer and explanation

    Correct answer: C