Certified ScrumMaster Free Sample Questions

Description

Covers empirical process control and Scrum values, the Scrum team and its accountabilities, sprint events from planning to the daily Scrum, product and sprint backlogs, and scaling Scrum adoption.

20 free sample questions203 in the full practice test

Try simulator

CSM Sample Questions

  1. Question 1

    Beginner

    Scrum Theory and Values · Applying Scrum Values to Team Interactions

    A Scrum Team has just completed its first Sprint. During the Sprint Retrospective, the Developers express frustration that they were constantly interrupted by stakeholders asking for status updates. Which of the five Scrum Values is most directly compromised by this situation?

    Answer and explanation

    Correct answer: B

    The value of 'Focus' is most directly compromised. By allowing frequent interruptions, the team loses its ability to concentrate on the work of the Sprint and progress towards the Sprint Goal. The Scrum Master should coach the stakeholders on how to interact with the team appropriately, likely directing communication through the Product Owner and respecting the Sprint's boundary.

  2. Question 2

    Beginner

    Scrum Theory and Values · Understanding Empiricism

    True or False: The three pillars of empiricism require that the process and work must be visible to those performing the work as well as those receiving the work.

    Answer and explanation

    Correct answer: A

    This statement is true. It directly describes the pillar of Transparency. For inspection and adaptation to be effective, the state of the artifacts and progress towards goals must be transparent to all involved parties, ensuring everyone operates from a common understanding.

  3. Question 3

    Intermediate

    Scrum Artifacts and Commitments · Product Goal

    A Product Owner is struggling to communicate the long-term direction for the product to the Scrum Team and stakeholders. This has resulted in Sprint Goals that feel disconnected from any larger objective. Which artifact's commitment is likely missing or poorly defined?

    Answer and explanation

    Correct answer: C

    The Product Goal is the commitment for the Product Backlog. It describes a future state of the product which can serve as a target for the Scrum Team to plan against. A missing or poorly defined Product Goal leads to a lack of long-term vision, causing Sprint Goals to seem random and tactical rather than strategic steps toward a larger objective.

  4. Question 4

    Intermediate

    Scrum Events · Facilitating Sprint Planning

    During Sprint Planning, the Developers determine they cannot complete all the high-priority items the Product Owner has proposed. The Product Owner is concerned about meeting stakeholder expectations. As the Scrum Master, what is the most appropriate action?

    Answer and explanation

    Correct answer: C

    The Scrum Master's role is to facilitate, not dictate. The Developers are accountable for selecting the amount of work they can complete. The most effective action is to facilitate a negotiation between the Product Owner and Developers to define a realistic Sprint Goal and corresponding Sprint Backlog. This respects the Developers' self-management and helps the Product Owner make necessary trade-offs.

  5. Question 5

    Advanced

    Scrum Theory and Values · Diagnosing Issues with Empiricism

    A Scrum Team is consistently delivering an Increment that meets the Definition of Done, but stakeholders in the Sprint Review remark that the delivered features are not what they actually need. This indicates a breakdown in which pillar of empiricism?

    Answer and explanation

    Correct answer: C

    While all pillars are related, the core issue is a failure to adapt. The Sprint Review is a key event for inspection and adaptation. Stakeholders provide feedback (inspection), and the expected outcome is that the Product Owner uses this feedback to adjust the Product Backlog for future Sprints (adaptation). If the team continues to build features that miss the mark, it means this adaptation loop is broken.

  6. Question 6

    IntermediateMultiple answers

    Scrum Team and Accountabilities · Scrum Master Service to the Organization

    A line manager who oversees several Developers on a Scrum Team approaches the Scrum Master. The manager is concerned about the team's performance and requests a report detailing the individual output and task completion times for each of their direct reports. How should the Scrum Master respond? (Select TWO).

    Answer and explanation

    Correct answers: B, D

    This addresses the manager's request by re-framing performance in a Scrum context, shifting the focus from individual metrics to team outcomes and collective ownership.

    This is a proactive coaching action. It helps the manager understand Scrum principles and provides a constructive, transparent way for them to observe the team's results without undermining self-management.

  7. Question 7

    Intermediate

    Scrum Artifacts and Commitments · Product Backlog Characteristics

    A new Product Owner, with a background in traditional project management, has created a Product Backlog that is structured like a Gantt chart, with dependencies and timelines assigned to each item. What is the primary risk of this approach?

    Answer and explanation

    Correct answer: B

    A core tenet of Scrum is empiricism, which relies on learning and adapting. A Gantt chart-style backlog creates a false sense of certainty and discourages change. The Product Backlog should be an emergent, ordered list that can be adapted at any time based on new insights, market changes, or feedback, which this rigid structure prevents.

  8. Question 8

    Beginner

    Scrum Artifacts and Commitments · Definition of Done

    Who is accountable for creating the Definition of Done?

    Answer and explanation

    Correct answer: C

    The entire Scrum Team is accountable for creating the Definition of Done. If the organization has a standard Definition of Done, the Scrum Team must follow it as a minimum and may add to it. This collective ownership ensures that everyone—Product Owner, Scrum Master, and Developers—shares a common understanding of what it means for work to be complete.

  9. Question 9

    Intermediate

    Scrum Team and Accountabilities · Scrum Team Size

    A Scrum Team has grown to 15 people. The Daily Scrums are consistently exceeding the 15-minute timebox, and communication has become complex and slow. According to the Scrum Guide, what is the recommended course of action?

    Answer and explanation

    Correct answer: C

    The Scrum Guide recommends that a Scrum Team be small enough to remain nimble, typically 10 or fewer people. Once a team grows too large, communication overhead increases, and agility diminishes. The best practice is to reorganize into multiple smaller Scrum Teams, each responsible for a cohesive set of work, often sharing the same Product Backlog and Product Owner.

  10. Question 10

    Advanced

    Scrum Team and Accountabilities · Collective Accountability

    An organization is transitioning to Scrum. A senior executive is concerned about the lack of a traditional Project Manager role and asks the Scrum Master who is responsible for the project's success. Which statement best describes accountability in a Scrum Team?

    graph TD subgraph ScrumTeam [Scrum Team] PO[Product Owner] SM[Scrum Master] Devs[Developers] end subgraph Accountabilities PO -- "Maximizing Value" --> PBacklog[Product Backlog] Devs -- "Creating Increment" --> SBacklog[Sprint Backlog] SM -- "Ensuring Effectiveness" --> Process[Scrum Process] ScrumTeam -- "Overall Accountability for Value" --> Increment[Valuable Increment] end

    Answer and explanation

    Correct answer: D

    Scrum replaces the single point of accountability of a Project Manager with the collective accountability of the entire Scrum Team. While each role has specific accountabilities (PO for value, Developers for quality Increment, SM for effectiveness), the team as a unit is accountable for delivering a valuable, useful Increment each Sprint. Success is a team effort and a shared responsibility.

Register free for 10 more questions

Or unlock all 203 CSM questions with explanations, timed mode and flashcards.