Question 1
BeginnerScrum Theory and Values · Applying Scrum Values to Team Interactions
A Scrum Team has just completed its first Sprint. During the Sprint Retrospective, the Developers express frustration that they were constantly interrupted by stakeholders asking for status updates. Which of the five Scrum Values is most directly compromised by this situation?
Answer and explanation
Correct answer: B
The value of 'Focus' is most directly compromised. By allowing frequent interruptions, the team loses its ability to concentrate on the work of the Sprint and progress towards the Sprint Goal. The Scrum Master should coach the stakeholders on how to interact with the team appropriately, likely directing communication through the Product Owner and respecting the Sprint's boundary.