A network engineer is designing a 1.2 km point-to-point wireless bridge using the 5 GHz band. A building under construction is located directly in the path, 0.5 km from one end. To ensure link reliability, 60% of the first Fresnel zone must remain clear of this obstruction. What is the minimum required height clearance above the building?