Question 1
An installer is performing a pre-installation site survey for a new Hitachi VSP E790 with two expansion drive boxes. The customer's data center uses top-of-rack power distribution units (PDUs) with IEC C19 outlets. The VSP E790 requires four power connections for the controller chassis and two for each drive box. What is the primary power-related consideration the installer must verify with the data center manager?
Answer and explanation
Correct answer: B
The most critical power consideration is ensuring the total power draw (amperage) of the storage system does not overload the PDUs or the circuit breaker. While phase separation is a best practice for redundancy, exceeding the total capacity is a primary safety and operational risk that must be verified first. The number of outlets and network port availability are secondary concerns compared to the fundamental power capacity.