Question 1
Q1During a new AFF A250 installation, an engineer discovers that the customer-provided rack does not have sufficient Power Distribution Units (PDUs) to support the power requirements specified in the NetApp Hardware Universe. The customer suggests using lower-amperage splitters to accommodate the existing PDUs. What is the appropriate course of action for the installation engineer?
Show answer & explanation
Correct answer: B
The correct action is to halt the installation until the site's power infrastructure meets the specifications outlined in the NetApp Hardware Universe. Using underrated power equipment like splitters creates a significant risk of power failure and system instability, which violates installation best practices. The engineer has a responsibility to ensure the environment is suitable to support the hardware reliably.