  1. Question 1

    A government-funded infrastructure project is developing a new high-speed rail link. The project has a strong mandate to minimize its carbon footprint and deliver social value. During the 'Initiating a Project' process, the Project Manager is defining the project's performance targets. Which approach best demonstrates the application of the 'sustainability' project performance dimension?

    Answer and explanation

    Correct answer: B

    PRINCE2 7 introduces sustainability as a seventh project performance dimension, alongside cost, time, scope, quality, risk, and benefits. The best way to apply this is to set specific, measurable targets and tolerances for environmental, social, and governance (ESG) factors. This option directly addresses setting tolerances for environmental and social aspects, which is the correct application of the sustainability dimension.

  2. Question 2

    A project to implement a new CRM system is experiencing significant resistance from the sales team, who are comfortable with the old system. The Project Manager has observed a drop in morale and a lack of engagement in training sessions. According to the PRINCE2 7 guidance on people management, what should be the Project Manager's primary focus to address this situation?

    Answer and explanation

    Correct answer: C

    PRINCE2 7 places a central focus on people management, recognizing that successful change requires understanding and engaging with those affected. The most effective approach is to work collaboratively with the resistant stakeholders. This involves active listening, empathy, and demonstrating how the change will benefit them, thereby turning resistance into support. This aligns with leading successful change and effective stakeholder engagement.

  3. Question 3

    A project is established to develop a mobile banking app. The market is highly competitive, and speed to market is critical. The Project Board has decided to use an iterative delivery approach (e.g., Scrum). How should the 'manage by stages' principle be applied in this context?

    Answer and explanation

    Correct answer: C

    The 'manage by stages' principle is fundamental to PRINCE2 and provides control points for the Project Board. In an agile context, it is tailored. Treating each short sprint as a full management stage creates excessive overhead. The best practice is to have fewer, longer management stages (e.g., quarterly) that contain several delivery sprints. This allows the delivery team to work iteratively while providing the Project Board with appropriate governance and decision points without micromanagement.

  4. Question 4

    A pharmaceutical company is running a project to achieve regulatory approval for a new drug. The Project Initiation Documentation (PID) has been approved. Midway through a stage, a competitor announces a similar drug, which could significantly impact the project's business justification. What is the most appropriate immediate action for the Project Manager?

    Answer and explanation

    Correct answer: B

    The principle 'ensure continued business justification' is paramount. An event that threatens the Business Case is a major issue that cannot wait for a routine report. The correct procedure is to formally log it as an issue, perform an immediate impact analysis on the Business Case, and if the project's viability is now in question (an exception condition), the Project Manager must escalate this to the Project Board via an Exception Report for a decision.

  5. Question 5

    Multiple answers

    A project is implementing a new data analytics platform. The project team is using various cloud-based collaboration tools, and large datasets are being transferred between the supplier and the company. The Project Manager needs to create a Digital and Data Management Approach document. According to PRINCE2 7, which of the following elements should be included? (Select THREE)

    Answer and explanation

    Correct answers: B, C, E

    The Digital and Data Management Approach must define how data will be handled securely and in compliance with regulations.

    This approach document should specify the digital toolset for project execution and communication.

    This defines how project documentation (e.g., logs, reports, plans) will be handled in a digital environment.

  6. Question 6

    True or False: In a PRINCE2 7 project, the 'people' element is considered an integrated part of the method, influencing how principles, practices, and processes are applied, rather than being a separate, optional consideration.

    Answer and explanation

    Correct answer: A

    This statement is true. A key update in PRINCE2 7 is the integration of a central 'people' element. It's not a standalone topic but is woven into the fabric of the method, affecting how project managers should lead teams, engage stakeholders, and foster a positive project culture when applying all other parts of PRINCE2.

  7. Question 7

    A project to construct a new community center is being managed by a local council. The project is small, with a well-understood scope and a small, co-located team. The Project Manager is considering how to tailor the 'organizing' practice. Which of the following represents the most appropriate tailoring decision for this project's organization structure?

    Answer and explanation

    Correct answer: C

    Tailoring involves adapting the method to the project's environment, size, and complexity. For a small, straightforward project, it is common and appropriate to combine roles on the Project Board, provided there is no conflict of interest. If the budget holder (Executive accountability) is also the primary representative of the users, combining these roles is an efficient tailoring decision. This maintains the three essential interests (business, user, supplier) on the board without unnecessary bureaucracy.

  8. Question 8

    During the 'Closing a Project' process for a software development project, the team has produced a final Lessons Report. According to the 'learn from experience' principle, what is the primary purpose of this report?

    Answer and explanation

    Correct answer: D

    The 'learn from experience' principle is forward-looking. The primary purpose of the Lessons Report at the end of a project is to consolidate all lessons learned (both positive and negative) so that they can be reviewed and acted upon by the wider organization. This helps prevent future projects from repeating the same mistakes and allows them to adopt successful practices, thereby improving corporate capability.

  9. Question 9

    A project manager is leading a team composed of individuals from different functional departments who have never worked together before. There are early signs of conflict over working styles and communication norms. To foster a collaborative and high-performing team culture, which people management technique would be most effective to apply early in the project?

    Answer and explanation

    Correct answer: C

    PRINCE2 7 emphasizes the importance of proactively managing team dynamics. Co-creating a team charter is a powerful technique that gives the team ownership of their working agreements. It allows them to collectively decide on communication methods, meeting etiquette, and how to handle disagreements. This builds trust and creates a foundation for effective collaboration, directly addressing the identified conflicts.

  10. Question 10

    A project's goal is to reduce a factory's energy consumption by 20%. The Project Manager has identified a risk that new environmental regulations, scheduled to be announced in three months, might require a 30% reduction instead. The probability of this is high. Which risk response strategy is most appropriate for the Project Manager to recommend?

    Answer and explanation

    Correct answer: D

    A contingent plan (or 'Prepare contingent plans' response) is the most suitable strategy here. The event is uncertain but has a high probability. It would be inefficient to immediately increase the scope and cost to aim for 30% if it's not required. Instead, the project should plan for the possibility. This involves identifying the actions needed to reach the 30% target and setting them aside to be triggered only if the risk materializes.

Register free to unlock 10 more sample questions

Lifetime One

Own this practice test forever.

$79.99
$75.99
one-time
  • Full access to 193 questions
  • Study, Timed & Flashcard Modes
  • All past and future versions i
  • Detailed Explanations
  • Study Tracking & Past Attempts
  • Brainy AI Assistant
  • Lifetime updates

Two

Any 2 exams per month.

$20.00/exam
$39.99
/month
  • 2 active exam slots
  • Study, Timed & Flashcard Modes
  • All past and future versions i
  • Detailed Explanations
  • Study Tracking & Past Attempts
  • 1,000 Brainy AI Credits
  • Cancel anytime

Premium Twelve

Any 12 exams over 3 months.

$15.00/exam
$179.99
/3 months
  • 4 active exam slots
  • Study, Timed & Flashcard Modes
  • All past and future versions i
  • Detailed Explanations
  • Study Tracking & Past Attempts
  • 15,000 Brainy AI Credits
  • Dedicated support
  • Friend seat included — full access

Trusted by professionals at

NvidiaSupabaseGitHubOpenAITursoClerkClaude AIAmazon