SAFe Advanced Scrum Master Free Sample Questions

20 free sample questions203 in the full practice test

Try simulator

sasm Sample Questions

  1. Question 1

    A newly formed Agile Release Train (ART) is struggling with alignment during its first PI Planning event. Teams are creating plans that have numerous cross-team dependencies, but they are not actively collaborating to resolve them, leading to a program board with many uncommitted objectives. What is the most effective initial action for an Advanced Scrum Master to take?

    Answer and explanation

    Correct answer: B

    The most effective initial action is to facilitate direct communication and problem-solving among the teams. A Scrum of Scrums during the breakout provides a dedicated forum for dependency management and negotiation, empowering the teams to self-organize and align their plans. Stopping the event is a drastic measure, escalating to management removes team ownership, and documenting dependencies without resolving them does not address the core issue of collaboration.

  2. Question 2

    An Agile team's lead time is increasing, and their cumulative flow diagram (CFD) shows a widening 'In Progress' band, indicating that Work in Process (WIP) is aging. The team feels constantly busy but delivers features unpredictably. Which flow accelerator should an Advanced Scrum Master coach the team to apply first?

    Answer and explanation

    Correct answer: C

    The primary cause of increasing lead time and aging WIP is having too many items in progress simultaneously. Visualizing the workflow and implementing explicit WIP limits forces the team to focus on completing existing work before starting new items. This directly tackles the problem described, improves predictability, and reduces context switching. While other accelerators are valuable, limiting WIP is the foundational first step for this specific scenario.

  3. Question 3

    During an Iteration Retrospective, two senior developers dominate the conversation, consistently shutting down suggestions from junior team members. This has led to a noticeable decrease in participation from the rest of the team. As an Advanced Scrum Master, what facilitation technique would be most effective to ensure all voices are heard and foster psychological safety?

    Answer and explanation

    Correct answer: C

    The '1-2-4-All' liberating structure is specifically designed to address this type of dysfunction. It allows for individual, silent reflection first (1), ensuring that everyone's initial thoughts are captured without being influenced or shut down by dominant personalities. The subsequent sharing in pairs (2), then fours (4), and finally with the whole group (All) creates a safer, more structured environment for all ideas to be heard and considered. This directly promotes psychological safety and balanced participation.

  4. Question 4

    An Agile Release Train is conducting its first Inspect and Adapt (I&A) workshop. The teams have successfully completed the quantitative measurement part of the event. What is the primary purpose of the problem-solving workshop that follows?

    Answer and explanation

    Correct answer: B

    The problem-solving workshop's main goal is to move beyond symptoms and perform a root cause analysis (e.g., using Fishbone diagrams or 5 Whys) on the most significant challenges the ART faced during the Program Increment. The outcome is a set of actionable improvement items that are added to the ART backlog to be worked on in the next PI, fostering relentless improvement.

  5. Question 5

    True or False: In SAFe, the primary responsibility for resolving dependencies between teams on an Agile Release Train lies with the Release Train Engineer.

    Answer and explanation

    Correct answer: B

    This statement is false. While the Release Train Engineer (RTE) facilitates dependency management and helps remove impediments, the primary responsibility lies with the Agile teams themselves. SAFe promotes self-organization and decentralized decision-making, encouraging teams to communicate and resolve dependencies directly with each other, especially during PI Planning.

  6. Question 6

    Multiple answers

    An ART is experiencing significant delays due to the high number of handoffs required to get a feature through the continuous delivery pipeline. The current process is visualized below:

    [Dev Team] → [QA Team] → [SecOps Team] → [Ops Team]
    | | | |
    Code Manual Test Security Scan Manual Deploy
    

    Which TWO SAFe DevOps principles would most directly address this flow impediment? (Select TWO)

    Answer and explanation

    Correct answers: A, B

  7. Question 7

    Case Study:

    A healthcare technology company, HealthFirst, has been using SAFe for over a year. One of their Agile Release Trains, 'PatientPortals', consistently struggles to meet its PI Objectives. During the latest Inspect & Adapt workshop, a root cause analysis revealed that the ART is comprised of component teams (UI, Backend, Database) rather than feature teams. This structure creates a high number of dependencies for every new feature, with work having to be coordinated and passed between three separate backlogs and teams. The flow of value is slow and riddled with delays and rework.

    The ART leadership is hesitant to restructure the teams due to perceived risks of losing specialized expertise and the disruption it would cause. They believe the current process just needs better coordination. The RTE and Product Management have asked the Advanced Scrum Masters on the ART to propose a strategy to address this systemic issue.

    Which proposal represents the most effective, long-term solution for the Advanced Scrum Masters to champion?

    Answer and explanation

    Correct answer: B

    This approach addresses the root cause (team structure) while mitigating the risks perceived by leadership. A gradual, pilot-based transition allows the organization to learn and adapt. Using value stream mapping provides objective data to build a compelling case for change by visualizing the waste in the current system and quantifying the benefits of organizing around value with feature teams. This is a strategic, coaching-based approach that respects leadership's concerns while guiding them toward a more effective solution.

  8. Question 8

    During PI Planning, a team identifies a significant risk that they cannot mitigate on their own, as it involves a dependency on an external vendor's deliverables. According to SAFe, how should this risk be categorized and handled on the ROAM board?

    Answer and explanation

    Correct answer: A

  9. Question 9

    A mature Agile team has mastered Scrum practices and is consistently delivering value. However, their Iteration Retrospectives have become stale, often repeating the same discussions with little impact. What is the best way for an Advanced Scrum Master to re-energize the team's relentless improvement efforts?

    Answer and explanation

    Correct answer: B

    Stale retrospectives are a common problem. An Advanced Scrum Master should act as a coach and facilitator by introducing variety. Changing the format (e.g., Speedboat, Starfish, 4Ls) and focusing the discussion on a specific, higher-level concept like a SAFe Core Value can help the team look at their process from a new perspective, generating fresh insights and more meaningful improvement actions.

  10. Question 10

    An ART is trying to improve its flow by managing queue lengths. Which of the following is the most direct negative consequence of having long queues of work waiting in the backlog?

    Answer and explanation

    Correct answer: B

    Long queues mean that there is a significant delay between when an item is identified and when work on it begins. In a dynamic business environment, this delay increases the risk that customer needs, market conditions, or priorities will change, rendering the queued item obsolete or less valuable by the time the team is ready to work on it. This directly impacts the delivery of value.

Register free to unlock 10 more sample questions

Lifetime One

Own this practice test forever.

$79.99
$75.99
one-time
  • Full access to 203 questions
  • Study, Timed & Flashcard Modes
  • All past and future versions i
  • Detailed Explanations
  • Study Tracking & Past Attempts
  • Brainy AI Assistant
  • Lifetime updates

Two

Any 2 exams per month.

$20.00/exam
$39.99
/month
  • 2 active exam slots
  • Study, Timed & Flashcard Modes
  • All past and future versions i
  • Detailed Explanations
  • Study Tracking & Past Attempts
  • 1,000 Brainy AI Credits
  • Cancel anytime

Premium Twelve

Any 12 exams over 3 months.

$15.00/exam
$179.99
/3 months
  • 4 active exam slots
  • Study, Timed & Flashcard Modes
  • All past and future versions i
  • Detailed Explanations
  • Study Tracking & Past Attempts
  • 15,000 Brainy AI Credits
  • Dedicated support
  • Friend seat included — full access

Trusted by professionals at

NvidiaSupabaseGitHubOpenAITursoClerkClaude AIAmazon