Q1

A manufacturing company is implementing Production Planning and Detailed Scheduling (PP/DS) in SAP S/4HANA. They require that high-priority customer orders automatically preempt production capacity from lower-priority planned orders during the nightly planning run. Which combination of PP/DS tool and configuration is best suited to achieve this dynamic reprioritization?

Q2

A medical device manufacturer uses date effectivity via change numbers to manage engineering updates to their product BOMs. A new regulation requires a specific component to be replaced starting from a future production date. When a planner creates a production order with a start date after the change number's 'valid from' date, the system still selects the old component. What is the most likely reason for this issue?

Q3

A company is implementing Lean Manufacturing and wants to use KANBAN for replenishing components in a production supply area (PSA). They need to ensure that the KANBAN quantity automatically adjusts based on fluctuations in daily demand and changes in the component's replenishment lead time. Which KANBAN procedure should be configured?

Q4Multiple answers

During a production order confirmation using a Fiori app, a user reports that component backflushing failed. An analysis in the 'Reprocess Goods Movements' (COGI) transaction shows a deficit of stock in the specified production storage location. Investigation reveals that sufficient unrestricted-use stock is available in a central warehouse storage location within the same plant. Which configuration elements must be in place to allow the system to automatically consume the stock from the central warehouse during confirmation? (Select THREE)

Q5

A planner is using the MRP Live (MD01n) transaction in SAP S/4HANA. They need to run regenerative planning for a specific set of materials that are managed by a single MRP controller, without affecting other materials. Which parameters should they use?

Q6

In a process manufacturing scenario, a company must ensure that an electronic signature is captured when the Quality department approves the final process phase. This action should automatically post the goods receipt for the finished product. Which objects must be configured and linked to enable this functionality?

Q7

A company uses make-to-stock production. Planners have noticed that the system creates new planned orders for requirements that are very close to the current date, inside the production lead time, leading to constant rescheduling and production instability. They want to create a stability period where the system will not create new procurement proposals. Which planning strategy parameter should be used for this purpose?

Q8

When defining a work center for capacity planning, what is the primary purpose of the 'Formulas' assigned in the capacity header?

Q9

True or False: In SAP S/4HANA, the 'Clean Core' principle encourages modifying standard SAP code to meet unique business requirements, as long as the modifications are well-documented.

Q10Multiple answers

A key difference between classic MRP in SAP ERP and MRP Live in SAP S/4HANA is that MRP Live is optimized for performance on the HANA database. Which of the following capabilities is a direct result of this optimization? (Select TWO)