SAP C-TS422-2023 Free Sample Questions

Description

Covers clean core principles, supply chain and production planning, demand forecasting, PP/DS, capacity planning, lean manufacturing, bills of material, production orders, and MRP.

20 free sample questions208 in the full practice test

Try simulator

C-TS422-2023 Sample Questions

  1. Question 1

    Advanced

    Advanced Planning in SAP S/4HANA · PP/DS Heuristics and Strategy Profiles

    A manufacturing company is implementing Production Planning and Detailed Scheduling (PP/DS) in SAP S/4HANA. They require that high-priority customer orders automatically preempt production capacity from lower-priority planned orders during the nightly planning run. Which combination of PP/DS tool and configuration is best suited to achieve this dynamic reprioritization?

    Answer and explanation

    Correct answer: B

    The most efficient way to handle this requirement is by using a planning heuristic combined with a correctly configured strategy profile. The strategy profile allows you to define priorities for different demand categories (like sales orders vs. forecasts). Setting 'Sales Order' as the top priority and enabling the 'Insert operations' or 'Reschedule operations' setting ensures the heuristic will automatically de-allocate and reschedule capacity from lower-priority orders to fulfill high-priority demands. The optimizer could also work but is more complex to set up and computationally intensive for a standard nightly run. A background MRP Live run and fixing pegging relationships are related but do not directly address the automatic preemption of capacity.

  2. Question 2

    Advanced

    Master Data in SAP S/4HANA · Bill of Material (BOM) with Change Management

    A medical device manufacturer uses date effectivity via change numbers to manage engineering updates to their product BOMs. A new regulation requires a specific component to be replaced starting from a future production date. When a planner creates a production order with a start date after the change number's 'valid from' date, the system still selects the old component. What is the most likely reason for this issue?

    Answer and explanation

    Correct answer: C

    Even if the change number is correctly configured, the production version itself plays a key role. If the production version selected for the order has a validity that starts before the change number's effectivity and is not set up to be sensitive to engineering change management, the system may use the BOM structure that was valid when the production version was created or last maintained. To resolve this, the existing production version might need to be updated with a new validity period or a new production version created that is valid from the change number's effective date.

  3. Question 3

    Intermediate

    Lean Manufacturing in SAP S/4HANA · KANBAN Calculation Procedures

    A company is implementing Lean Manufacturing and wants to use KANBAN for replenishing components in a production supply area (PSA). They need to ensure that the KANBAN quantity automatically adjusts based on fluctuations in daily demand and changes in the component's replenishment lead time. Which KANBAN procedure should be configured?

    Answer and explanation

    Correct answer: D

    The automatic KANBAN calculation based on dependent requirements is specifically designed for this purpose. The system analyzes the dependent requirements (generated by MRP from planned/production orders for finished goods) within a specified evaluation period. It then proposes the number of KANBANs and the KANBAN quantity needed to cover that demand, considering the replenishment lead time and a safety factor. This allows the KANBAN loop to be self-adjusting to actual demand fluctuations.

  4. Question 4

    IntermediateMultiple answers

    Production Orders in SAP S/4HANA · Stock Determination and Goods Movement

    During a production order confirmation using a Fiori app, a user reports that component backflushing failed. An analysis in the 'Reprocess Goods Movements' (COGI) transaction shows a deficit of stock in the specified production storage location. Investigation reveals that sufficient unrestricted-use stock is available in a central warehouse storage location within the same plant. Which configuration elements must be in place to allow the system to automatically consume the stock from the central warehouse during confirmation? (Select THREE)

    Answer and explanation

    Correct answers: A, C, D

  5. Question 5

    Beginner

    Material Requirements Planning in SAP S/4HANA · MRP Live Execution

    A planner is using the MRP Live (MD01n) transaction in SAP S/4HANA. They need to run regenerative planning for a specific set of materials that are managed by a single MRP controller, without affecting other materials. Which parameters should they use?

    Answer and explanation

    Correct answer: C

    Regenerative planning is achieved by using Planning Mode '3 - Delete and Recreate Planning Data', which re-explodes the BOM and routings for all selected materials. To limit the scope of the run to materials managed by a specific MRP controller, a filter must be applied in the 'Material Scope' section of the MRP Live parameters. This ensures only the intended materials are planned.

  6. Question 6

    Advanced

    Process Orders in SAP S/4HANA · Process Messages and Digital Signatures

    In a process manufacturing scenario, a company must ensure that an electronic signature is captured when the Quality department approves the final process phase. This action should automatically post the goods receipt for the finished product. Which objects must be configured and linked to enable this functionality?

    Answer and explanation

    Correct answer: B

    This functionality is achieved through process management. A process instruction (PI) category is defined in the master recipe for the final phase. This PI category is configured to require a digital signature. Upon successful signature, it sends a process message (such as PI_PROD for goods receipt) to a defined destination. The system then processes this message to automatically post the goods movement. This ensures GMP compliance by linking the approval action directly to the system transaction.

  7. Question 7

    Intermediate

    Demand Management in SAP S/4HANA · Planning Time Fence

    A company uses make-to-stock production. Planners have noticed that the system creates new planned orders for requirements that are very close to the current date, inside the production lead time, leading to constant rescheduling and production instability. They want to create a stability period where the system will not create new procurement proposals. Which planning strategy parameter should be used for this purpose?

    Answer and explanation

    Correct answer: B

    The Planning Time Fence (PTF) is a period defined in the material master (in days) extending from the current date. Within this period, the planning run (MRP) is restricted from automatically creating or changing procurement proposals. This creates a 'frozen' or 'firm' zone, providing stability for production scheduling and procurement in the short term. The system can be configured to either create no new proposals or place them at the end of the time fence.

  8. Question 8

    Beginner

    Capacity Planning in SAP S/4HANA · Work Center Capacity Configuration

    When defining a work center for capacity planning, what is the primary purpose of the 'Formulas' assigned in the capacity header?

    Answer and explanation

    Correct answer: B

    Formulas in the work center are used to calculate execution time, costs, and capacity requirements for operations performed at that work center. These formulas use the standard values (e.g., setup time, machine time, labor time) entered in the routing operation and multiply them by the operation quantity to determine the total capacity load and duration.

  9. Question 9

    Beginner

    Managing Clean Core · Clean Core Principles

    True or False: In SAP S/4HANA, the 'Clean Core' principle encourages modifying standard SAP code to meet unique business requirements, as long as the modifications are well-documented.

    Answer and explanation

    Correct answer: B

    The Clean Core principle is fundamentally about avoiding modifications to standard SAP code. Instead, it promotes using modern, upgrade-safe extensibility options such as in-app extensibility (e.g., custom fields and logic) and side-by-side extensions on the SAP Business Technology Platform (BTP). This approach ensures smoother upgrades and lower total cost of ownership.

  10. Question 10

    IntermediateMultiple answers

    Material Requirements Planning in SAP S/4HANA · MRP Live vs Classic MRP

    A key difference between classic MRP in SAP ERP and MRP Live in SAP S/4HANA is that MRP Live is optimized for performance on the HANA database. Which of the following capabilities is a direct result of this optimization? (Select TWO)

    Answer and explanation

    Correct answers: A, D

Register free for 10 more questions

Or unlock all 208 C-TS422-2023 questions with explanations, timed mode and flashcards.