Question 1
Q1You are leading a network automation project to migrate legacy switch configurations to a controller-based architecture. According to IEEE 29148-2018, you are currently in the process of ensuring that the set of requirements accurately reflects the stakeholders' needs and that the specified system will solve the right problem. Which process are you performing?
Show answer & explanation
Correct answer: B
According to IEEE 29148-2018, Requirements Validation is the process of confirming that the requirements define the right system to meet stakeholder needs (building the right system). Requirements Verification, in contrast, ensures the requirements are written correctly and conform to standards (building the system right).