Question 1
Q1A project manager is evaluating the performance of two teams, Team A and Team B. Team A completes tasks at a rate of 'x' tasks per hour. Team B completes tasks at a rate of 'y' tasks per hour. When working together on a project of 100 tasks, they finish in 'T' hours. If Team A were to work alone, it would take them (T + 15) hours to complete the project. If x = 4, what is the value of y?
Show answer & explanation
Correct answer: B
Let the total work be 100 tasks. Team A's rate is x=4 tasks/hr. Team B's rate is y tasks/hr. The combined rate is (4+y). The time taken together is T = 100/(4+y). Time for Team A alone is 100/4 = 25 hours. We are given that Team A alone takes (T+15) hours. So, 25 = T + 15, which means T = 10 hours. Now substitute T back into the combined work equation: 10 = 100/(4+y). This simplifies to 10(4+y) = 100, so 40 + 10y = 100. Then 10y = 60, and y = 6.