PK0-004 Sample Questions

  1. Question 1

    A project manager is attempting to establish the proper sequencing and duration of project activities.

    Which of the following would be the MOST beneficial?

    Answer and explanation

    Correct answer: C

    A--Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 160

  2. Question 2

    Multiple answers

    The quarterly financial statement has been released, and portfolios are losing funding for projects.

    Which of the following options are MOST appropriate to keep the project alive and on schedule? (Choose two.)

    Answer and explanation

    Correct answers: B, C

    B,C

  3. Question 3

    Which of the following describes the difference between an acquisition and outsourcing?

    Answer and explanation

    Correct answer: A

    A

  4. Question 4

    Team members in a projectized organization are released at the end of a project and placed on the “bench”.

    Which of the following should the benched team members do NEXT?

    Answer and explanation

    Correct answer: A

    A

  5. Question 5

    Multiple answers

    Which of the following features describe a projectized organization? (Choose two.)

    Answer and explanation

    Correct answers: B, E

    B,E

  6. Question 6

    An American publisher is participating in a workshop in Hong Kong with the purpose of updating a new book that will be launched in Japan next year. During the workshop, a deep and intense discussion occurs with other local publishers regarding the references the book may contain.

    Which of the following BEST describes the situation?

    Answer and explanation

    Correct answer: B

    B

  7. Question 7

    A subcontractor has submitted design documentation on the deliverable due date, but it will require rework. The activity is on the critical path of the project schedule.

    Which of the following should the project manager do NEXT?

    Answer and explanation

    Correct answer: C

    C

  8. Question 8

    The project team is distributed throughout a single country. The scrum master has decided to hold remote "stand-ups" on a daily basis.

    Which of the following would be the MOST effective means to do this?

    Answer and explanation

    Correct answer: D

    D

  9. Question 9

    Which of the following defines a group of projects that work together to achieve a common goal?

    Answer and explanation

    Correct answer: B

    B--Reference: Kim Heldman, CompTIA Projects- Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 71

  10. Question 10

    Due to a new government regulation, a project change is required. The project manager evaluates the change and realizes a representative from the legal department will need to approve the change as well.

    The project manager should:

    Answer and explanation

    Correct answer: D

    D--Reference: Kim Heldman, CompTIA Project* Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 294