  1. Question 1

    Q1

    A project manager is attempting to establish the proper sequencing and duration of project activities.

    Which of the following would be the MOST beneficial?

    Show answer & explanation

    Correct answer: C

    A--Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 160

  2. Question 2

    Q2Multiple answers

    The quarterly financial statement has been released, and portfolios are losing funding for projects.

    Which of the following options are MOST appropriate to keep the project alive and on schedule? (Choose two.)

    Show answer & explanation

    Correct answers: B, C

    B,C

  3. Question 3

    Q3

    Which of the following describes the difference between an acquisition and outsourcing?

    Show answer & explanation

    Correct answer: A

    A

  4. Question 4

    Q4

    Team members in a projectized organization are released at the end of a project and placed on the “bench”.

    Which of the following should the benched team members do NEXT?

    Show answer & explanation

    Correct answer: A

    A

  5. Question 5

    Q5Multiple answers

    Which of the following features describe a projectized organization? (Choose two.)

    Show answer & explanation

    Correct answers: B, E

    B,E

  6. Question 6

    Q6

    An American publisher is participating in a workshop in Hong Kong with the purpose of updating a new book that will be launched in Japan next year. During the workshop, a deep and intense discussion occurs with other local publishers regarding the references the book may contain.

    Which of the following BEST describes the situation?

    Show answer & explanation

    Correct answer: B

    B

  7. Question 7

    Q7

    A subcontractor has submitted design documentation on the deliverable due date, but it will require rework. The activity is on the critical path of the project schedule.

    Which of the following should the project manager do NEXT?

    Show answer & explanation

    Correct answer: C

    C

  8. Question 8

    Q8

    The project team is distributed throughout a single country. The scrum master has decided to hold remote "stand-ups" on a daily basis.

    Which of the following would be the MOST effective means to do this?

    Show answer & explanation

    Correct answer: D

    D

  9. Question 9

    Q9

    Which of the following defines a group of projects that work together to achieve a common goal?

    Show answer & explanation

    Correct answer: B

    B--Reference: Kim Heldman, CompTIA Projects- Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 71

  10. Question 10

    Q10

    Due to a new government regulation, a project change is required. The project manager evaluates the change and realizes a representative from the legal department will need to approve the change as well.

    The project manager should:

    Show answer & explanation

    Correct answer: D

    D--Reference: Kim Heldman, CompTIA Project* Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 294

Register free to unlock 10 more sample questions

Create a free account to continue with the rest of the PK0-004 sample set.

Lifetime One

Own this practice test forever.

$79.99
$75.99
one-time
  • Full access to 734 questions
  • Study, Timed & Flashcard Modes
  • All past and future versions i
  • Detailed Explanations
  • Study Tracking & Past Attempts
  • Brainy AI Assistant
  • Lifetime updates

Two

Any 2 exams per month.

$20.00/exam
$39.99
/month
  • 2 active exam slots
  • Study, Timed & Flashcard Modes
  • All past and future versions i
  • Detailed Explanations
  • Study Tracking & Past Attempts
  • 1,000 Brainy AI Credits
  • Cancel anytime

Premium Twelve

Any 12 exams over 3 months.

$15.00/exam
$179.99
/3 months
  • 4 active exam slots
  • Study, Timed & Flashcard Modes
  • All past and future versions i
  • Detailed Explanations
  • Study Tracking & Past Attempts
  • 15,000 Brainy AI Credits
  • Dedicated support
  • Friend seat included — full access

Trusted by professionals at

NvidiaSupabaseGitHubOpenAITursoClerkClaude AIAmazon