CompTIA Project+ (v5) Free Sample Questions

Description

Covers project methodologies, change control and risk management, discovery, initiation and planning phases, project and productivity tools, and ESG, information security and compliance basics.

29 free sample questions235 in the full practice test Other version: PK0-004(499)

Try simulator

PK0-005 Sample Questions

  1. Question 1

    Intermediate

    A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization’s reluctance could jeopardize the success of the project. Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Choose two.)

    Answer and explanation

    Correct answer: A

  2. Question 2

    Intermediate

    Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the survey results as an input?

    Answer and explanation

    Correct answer: C

  3. Question 3

    Intermediate

    Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?

    Answer and explanation

    Correct answer: D

  4. Question 4

    Intermediate

    During a quality analysis review, the causes of several issues have been highlighted. Which of the following should the project manager use to identify the MOST important causes?

    Answer and explanation

    Correct answer: C

  5. Question 5

    Intermediate

    Which of the following BEST describes how an organization should coordinate management of multiple related projects?

    Answer and explanation

    Correct answer: B

  6. Question 6

    Intermediate

    A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?

    Answer and explanation

    Correct answer: D

  7. Question 7

    Intermediate

    A project manager prefers to have immediate contact with team members because it allows for faster response times and more interactive discussions. Which of the following communication methods should the project manager use?

    Answer and explanation

    Correct answer: A

  8. Question 8

    Intermediate

    As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?

    Answer and explanation

    Correct answer: C

  9. Question 9

    Intermediate

    A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?

    Answer and explanation

    Correct answer: A

  10. Question 10

    Advanced

    Basics of IT and Governance · Compliance requirements (GDPR, HIPAA, SOX)

    A financial technology firm is migrating its on-premises legacy payment processing system to a cloud-native microservices architecture. The Chief Information Security Officer (CISO) mandates strict adherence to data sovereignty laws due to international customer data. During the planning phase, which architecture decision BEST addresses the CISO's concern regarding data residency?

    Answer and explanation

    Correct answer: A

    Data sovereignty requires that data is subject to the laws of the country in which it is located. In a cloud environment, implementing a multi-region deployment strategy allows the organization to explicitly configure storage services to keep data within specific geographic boundaries (e.g., storing EU customer data solely in EU-based data centers) to comply with local regulations like GDPR.