PMI Scheduling Professional Free Sample Questions

Description

Covers schedule configuration management and policies, work breakdown structure and activity duration estimation, schedule monitoring and audits, schedule closeout, and stakeholder communication.

20 free sample questions249 in the full practice test

Try simulator

PMI-SP Sample Questions

  1. Question 1

    Intermediate

    Schedule Strategy · Establish Schedule Approach

    A Scheduling Professional is establishing the scheduling approach for a complex infrastructure project with high regulatory compliance requirements. The project charter dictates strict adherence to a fixed deadline due to government funding. Which scheduling methodology should be selected to best manage the critical path while ensuring all regulatory activities are documented and tracked?

    Answer and explanation

    Correct answer: B

    The Critical Path Method (CPM) is the optimal choice for projects with strict deadlines and regulatory requirements where specific activity sequences and the longest path (critical path) must be strictly managed to ensure on-time completion. CPM provides the necessary granularity for regulatory documentation.

  2. Question 2

    Advanced

    Schedule Strategy · Establish Schedule Objectives and Goals

    During the development of the Schedule Management Plan, the team is defining how schedule contingencies will be handled. Which component of the plan should explicitly detail the procedures for accessing management reserves versus contingency reserves?

    Answer and explanation

    Correct answer: C

    The Schedule Change Control Procedures within the Schedule Management Plan define how changes to the schedule baseline are managed, including the specific governance required to access management reserves (for unforeseen risks) versus contingency reserves (for identified risks).

  3. Question 3

    Beginner

    Schedule Strategy · Establish Schedule Approach

    True or False: In Rolling Wave Planning, work to be performed in the near term is planned in detail, while work in the future is planned at a higher level of the WBS.

    Answer and explanation

    Correct answer: A

    This is the definition of Rolling Wave Planning, an iterative planning technique where the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level.

  4. Question 4

    Beginner

    Schedule Planning and Development · Estimate Durations and Resources

    A project manager is determining the appropriate level of accuracy for activity duration estimates during the initiation phase. Which of the following ranges typically represents a Rough Order of Magnitude (ROM) estimate?

    Answer and explanation

    Correct answer: C

    According to the PMBOK Guide, a Rough Order of Magnitude (ROM) estimate is typically in the range of -25% to +75%. This is used early in the project when details are scarce.

  5. Question 5

    IntermediateMultiple answers

    Schedule Planning and Development · Decompose Work and Define Activities

    You are decomposing the project scope to create the schedule. Which TWO items are primary outputs of the 'Define Activities' process? (Select TWO)

    Answer and explanation

    Correct answers: C, D

    The Activity List is a comprehensive list including all schedule activities required on the project.

    Activity Attributes extend the description of the activity by identifying multiple components associated with each activity.

  6. Question 6

    Intermediate

    Schedule Strategy · Establish Schedule Objectives and Goals

    An organization requires that all schedule variances exceeding 10% be reported to the steering committee. In which document should this threshold be explicitly defined?

    Answer and explanation

    Correct answer: A

    The Schedule Management Plan establishes the criteria and the activities for developing, monitoring, and controlling the schedule. This includes control thresholds for variance reporting.

  7. Question 7

    Intermediate

    Schedule Strategy · Establish Schedule Approach

    A scheduler is advising a project team on setting up their schedule model. The project involves high uncertainty and evolving requirements. Which scheduling approach would allow for high-level planning of the overall timeline while detailing only the immediate iteration?

    Answer and explanation

    Correct answer: A

    Adaptive (or Agile) scheduling uses iterative and incremental planning. It works best for projects with high uncertainty, where detailed planning is done only for the upcoming iteration.

  8. Question 8

    Advanced

    Schedule Planning and Development · Develop and Optimize Schedule

    Consider the following network diagram logic:

    Activity A (5 days) -> Activity B (4 days)
    Activity A (5 days) -> Activity C (6 days)
    Activity B (4 days) -> Activity D (5 days)
    Activity C (6 days) -> Activity D (5 days)

    What is the Free Float of Activity B?

    Answer and explanation

    Correct answer: C

    Path 1: A-B-D = 5+4+5 = 14 days.
    Path 2: A-C-D = 5+6+5 = 16 days (Critical Path).
    Early Start of D is 11 (after C finishes at 5+6=11).
    Early Finish of B is 9 (5+4).
    Free Float of B = ES of successor (D) - EF of B = 11 - 9 = 2 days.

    graph LR A[A: 5d] --> B[B: 4d] A --> C[C: 6d] B --> D[D: 5d] C --> D
  9. Question 9

    Intermediate

    Schedule Planning and Development · Sequence Activities and Network Diagrams

    When defining activities for a new software module, the team identifies a 'Finish-to-Start' relationship between 'Code Module' and 'Test Module'. However, the testing team states they can begin testing the initial components 2 days before coding is fully complete. Which dependency modification best represents this scenario?

    Answer and explanation

    Correct answer: C

    A Lead allows a successor activity to start before the predecessor has finished. A 2-day lead on a Finish-to-Start relationship means testing can start 2 days before coding finishes.

  10. Question 10

    Intermediate

    Schedule Planning and Development · Estimate Durations and Resources

    You are using the Three-Point Estimating (Beta/PERT) technique. An activity has an Optimistic estimate of 4 days, a Most Likely estimate of 7 days, and a Pessimistic estimate of 16 days. What is the expected duration?

    Answer and explanation

    Correct answer: B

    The PERT Beta formula is (O + 4M + P) / 6.
    (4 + 4(7) + 16) / 6 = (4 + 28 + 16) / 6 = 48 / 6 = 8 days.

Register free for 10 more questions

Or unlock all 249 PMI-SP questions with explanations, timed mode and flashcards.