  1. Question 1

    A project to develop a new sustainable packaging solution is in its second stage. The project manager learns that a new, more biodegradable raw material has become available, which was not considered in the original business case. This new material could significantly improve the project's sustainability benefits but will increase the stage costs by 15%, exceeding the cost tolerance. According to PRINCE2, what is the project manager's most appropriate immediate action?

    Answer and explanation

    Correct answer: B

    This is the correct action. The forecasted breach of cost tolerance constitutes an exception. The project manager must not act unilaterally but must escalate the situation to the project board via an exception report. Logging it as an issue ensures it is formally tracked. The exception report will present the situation, analyze the impact on the business case (including the new sustainability benefits), and provide options for the project board to decide upon.

  2. Question 2

    During the 'initiating a project' process for a software development project, the project manager is defining the project management team structure. The lead developer is highly experienced technically but has poor communication skills and is resistant to formal reporting. The project manager is considering assigning a junior developer, who is an excellent communicator, to act as the team manager. Which aspect of the new PRINCE2 7 'people' element is most critical for the project manager to address in the role descriptions?

    Answer and explanation

    Correct answer: C

    PRINCE2 7 emphasizes the 'people' element, including defining relationships. The key challenge here is not just the tasks but the interpersonal dynamics. The role descriptions must explicitly define how the technical authority (lead developer) and the management authority (team manager) will interact, communicate, and make decisions. This clarifies authority and prevents conflict, directly addressing the identified people-related risk.

  3. Question 3

    A project is implementing a new digital asset management system. The project manager has been asked to tailor the PRINCE2 method. To increase efficiency, the project manager proposes that the project board will only meet at the end of each stage, and that the project manager will send highlight reports directly to the senior user on a weekly basis, bypassing other board members. Is this an appropriate application of the 'tailor to suit the project' principle?

    Answer and explanation

    Correct answer: C

    This tailoring is inappropriate because it undermines the governance structure and responsibilities of the project board. The executive and senior supplier have a right and a responsibility to be informed of project progress to provide effective direction. While tailoring is encouraged, it must not compromise key principles like 'define roles, responsibilities, and relationships' or the fundamental governance model. A highlight report's purpose is to inform the entire board, not just one member.

  4. Question 4

    A project board is reviewing the end stage report for the design stage of a new factory construction. The report shows the stage was completed on time and within budget. However, the risk register shows a new high-impact risk related to supply chain volatility for key construction materials. The next stage plan requires significant financial commitment. According to the 'manage by stages' principle, what is the primary purpose of this end stage assessment?

    Answer and explanation

    Correct answer: C

    The 'manage by stages' principle provides control points for the project board. At each stage boundary, the board's primary role is not just to review past performance but to look forward. They must review the updated business case and risk profile to decide if the project is still justified and worth the investment of the next stage. The new high-impact risk directly challenges the project's viability, making this review critical.

  5. Question 5

    True or False: According to the PRINCE2 'organizing' practice, the project manager is responsible for creating the benefits management approach.

    Answer and explanation

    Correct answer: A

    True. While the senior user is responsible for specifying the benefits and realizing them, the project manager is responsible for drafting the benefits management approach, which outlines how and when the project's benefits will be measured. This document is then approved by the project board.

  6. Question 6

    Multiple answers

    A project requires a highly specialized component from an external supplier. To ensure the component meets stringent performance requirements, which TWO of the following should be defined in its product description? (Select TWO)

    Answer and explanation

    Correct answers: C, D

    Quality criteria are measurable definitions of the product's quality attributes. They are essential for objective assessment.

    The quality method describes the specific tests, procedures, or checks that will be performed to verify that the quality criteria have been met.

  7. Question 7

    Case Study Scenario

    A national healthcare provider, HealthFirst, has initiated a project to create a centralized patient data platform. The goal is to consolidate patient records from various legacy systems into a single, secure, and accessible digital platform. The project is currently in the first delivery stage, focusing on developing the core database and data migration tools. The project has high visibility and is sponsored by the Chief Medical Officer, who is the project executive.

    The project manager, recently PRINCE2 7 certified, is establishing project controls. The digital and data management approach specifies that all patient data must be encrypted both at rest and in transit, adhering to strict national data privacy laws. A key specialist product is the 'Data Migration Module'. The team manager for the development team has reported that their initial tests of the module are successful in transferring data, but the encryption component is proving more complex than anticipated and is falling behind schedule.

    Simultaneously, a stakeholder group representing patient advocacy organizations has raised a formal issue, expressing concern about the security measures and requesting a third-party security audit before the system goes live. This was not originally included in the project plan or budget. The project manager foresees that incorporating this audit will delay the project and require additional funding, potentially threatening the business justification.

    Given the situation, how should the project manager apply the PRINCE2 practices of 'issues' and 'progress' to manage these challenges effectively?

    Answer and explanation

    Correct answer: B

    This is the most comprehensive and correct PRINCE2 approach. Both events are 'issues' that need to be formally managed. The encryption delay is an off-specification, and the audit request is a request for change. The 'issues' practice requires logging, examining, and assessing their impact. The 'progress' practice requires the project manager to analyze the impact on tolerances and the business case. Presenting a consolidated view in an issue report allows the project board (led by the Chief Medical Officer) to make an informed decision based on a full understanding of the situation and available options.

  8. Question 8

    A project is established to organize a major international conference. The project board has set tolerances for cost, time, and scope. During execution, the team manager reports that the keynote speaker has cancelled. Finding a replacement speaker of similar caliber will not increase costs or delay the conference date, but the new speaker's expertise is in a slightly different field than originally planned. How should the project manager first classify this event?

    Answer and explanation

    Correct answer: D

    This is an off-specification. The project's product (the conference) has a scope which included a specific type of keynote speaker. Even though time and cost tolerances are not threatened, the scope has been altered. This is a type of issue that must be formally logged and managed. The project manager needs to assess the impact of this change on the project's benefits and business justification, and may need to seek advice or a decision from the project board, even if it doesn't constitute a formal exception against the six tolerance areas.

  9. Question 9

    A project manager is preparing the PID for a project that involves handling sensitive customer data. The digital and data management approach has been created. Which PRINCE2 principle is most directly supported by the creation and maintenance of this new PRINCE2 7 management product?

    Answer and explanation

    Correct answer: D

    The digital and data management approach outlines the specific methods and standards for managing project information, including security and access. This directly supports the 'define roles, responsibilities, and relationships' principle by clarifying who is responsible for data management, who has access to what information, and the relationships between different project roles regarding project data.

  10. Question 10

    During the 'closing a project' process, the project manager discovers that a number of expected benefits have not yet been realized, as they are due to occur 6 months after the project's final product has been handed over. What is the correct action for the project manager to take regarding these benefits?

    Answer and explanation

    Correct answer: C

    A project is a temporary endeavor; it is not responsible for long-term benefits realization. The project manager's responsibility during closure is to evaluate the project against its baseline, document lessons, and prepare for handover. For future benefits, the project manager must ensure the benefits management approach contains a clear plan for who will measure them post-project and when. This plan is then handed over to the appropriate operational body (e.g., corporate management) as part of the project closure.

Register free to unlock 10 more sample questions

Lifetime One

Own this practice test forever.

$79.99
$75.99
one-time
  • Full access to 258 questions
  • Study, Timed & Flashcard Modes
  • All past and future versions i
  • Detailed Explanations
  • Study Tracking & Past Attempts
  • Brainy AI Assistant
  • Lifetime updates

Two

Any 2 exams per month.

$20.00/exam
$39.99
/month
  • 2 active exam slots
  • Study, Timed & Flashcard Modes
  • All past and future versions i
  • Detailed Explanations
  • Study Tracking & Past Attempts
  • 1,000 Brainy AI Credits
  • Cancel anytime

Premium Twelve

Any 12 exams over 3 months.

$15.00/exam
$179.99
/3 months
  • 4 active exam slots
  • Study, Timed & Flashcard Modes
  • All past and future versions i
  • Detailed Explanations
  • Study Tracking & Past Attempts
  • 15,000 Brainy AI Credits
  • Dedicated support
  • Friend seat included — full access

Trusted by professionals at

NvidiaSupabaseGitHubOpenAITursoClerkClaude AIAmazon