Q1

A project manager is leading a system conversion from SAP ECC 6.0 EHP8 to SAP S/4HANA 2023 On-Premise. The initial analysis from the SAP Readiness Check tool identifies over 5,000 simplification items. Which phase of the SAP Activate methodology is primarily dedicated to analyzing these items in detail and determining their disposition (e.g., adopt, replace, retire)?

Q2

During the setup of a new SAP S/4HANA Cloud implementation project, the project manager needs to ensure all project tasks, deliverables, and timelines are aligned with SAP's recommended practices for a cloud deployment. Which SAP tool provides pre-configured, phase-based roadmaps with accelerators and deliverable templates specifically for this purpose?

Q3

A company is planning a Selective Data Transition to SAP S/4HANA. They want to consolidate three legacy SAP ECC systems into a single S/4HANA client while migrating only the last three years of transactional data. Which SAP tool or service is specifically designed to manage this type of complex migration scenario?

Q4

True or False: The use of a 'Model Company' in an SAP Activate project is primarily intended for brownfield system conversion scenarios to replicate the existing system's configuration.

Q5Multiple answers

An agile team is consistently failing to complete all planned user stories within a sprint. During the sprint retrospective, the team identifies that user stories are often poorly defined and lack necessary details, causing rework. According to SAP Activate's agile principles, which two of the following are the most effective countermeasures? (Select TWO)

Q6

A project is adopting the 'clean core' principle for an SAP S/4HANA Cloud, Private Edition implementation. A critical business requirement cannot be met through standard configuration or existing APIs. What is the SAP-recommended approach for building this extension to maintain a clean core?

Q7

A project manager is creating the initial project plan for a greenfield SAP S/4HANA On-Premise implementation. The customer has a very aggressive timeline. To accelerate the Explore phase and provide the business with a tangible system to interact with early on, which SAP Activate accelerator should be prioritized?

Q8

In the context of an SAP Activate project, what is the primary purpose of the Solution Adoption workstream?

Q9

A project team is using SAP Cloud ALM for an SAP S/4HANA Cloud, public edition implementation. The project manager wants to ensure there is clear traceability from a business requirement to the deployed solution. Which SAP Cloud ALM capability is specifically designed to support this?

Q10

During the Prepare phase of an SAP S/4HANA implementation, the project team is defining the project governance model. Which of the following is a key deliverable of this activity?