Question 1
A business analyst for a retail company is examining a preliminary requirements register, shown below. While the register captures the business need and priority, the project manager states that it's insufficient for sprint planning with the agile development team. Which critical attribute is missing from this list that is essential for estimating work and planning iterations?
Answer and explanation
Correct answer: C
While acceptance criteria, value scores, and dependencies are all important attributes, the most critical missing piece for sprint planning is the estimated effort or size (e.g., in story points). The development team needs this information to determine how many items they can realistically commit to in an iteration. Without an estimate of size or complexity, capacity planning is impossible.