Question 1
IntermediateField Service Management Fundamentals · Work Order Lifecycle
A utility company is implementing ServiceNow FSM to manage emergency power outage responses. They need to ensure that when a 'Major Outage' work order is created, a predefined set of tasks for assessment, crew dispatch, and public communication is automatically generated. The tasks must have dependencies; for example, crew dispatch cannot begin until the initial assessment is complete. What is the most efficient way to configure this requirement?
Answer and explanation
Correct answer: B
Work Order Templates are the standard, out-of-the-box mechanism for creating a repeatable structure of work orders and tasks. They natively support defining task dependencies (Finish-to-Start, etc.), making them the ideal solution for this scenario. Using business rules or workflows would be a more complex and less maintainable customization.